This week, we have been welding, welding oh and wiring. Ha ha.
Well, all the cross members are now fully welded. All the unneeded holes have been welded. The last 2 outlet tubes have been welded and sanded smooth. A few more bits to welded, then we are on to the chassis top plates.
As for the wiring, well, as we are removing the ABS system, we needed to swap the entire engine bay loom. So the hunt for an engine bay loom from a non ABS rwd transit with the option of air-conditioning was on.
I managed to get hold of a loom from a friend. I compared the looms after removing the truck loom and we have managed to get the right one. There is a small repair as 1 plug is broken, but this is a small detail. Next, we need to remove the ABS unit and all the pipework. Also, we need to change the master cylinder to a non ABS one and then make up new brake pipes. There is still lots to do.
Sent from my SM-N981B using Tapatalk