i think this is the best way to do it
I've got some more comprehensive lists but i'll add those later when i'm better informed - i am getting advice from forum members on areas im unsure of
I might have missed jobs out in this list but dont worry - it doesnt mean i havent thought of them
The Basic Schedule
Thursday AM
Arrive on site set up
Thursday Afternoon
Strip van A down but leave axles on
Strip van B totally
chassis repairs to van A
Friday Day
Fit engine gearbox make all mounts etc. and remove before night
start making exhaust
Join back of Van B to van A
Work on all doors and bonnet off van
Refirb drive train off Van B
Interior – as much as possable
Friday Night
Spray engine bay and all door shuts, door backs etc.
Saturday Day
Refit engine
finish exhaust
Fit all refirb’d parts
Bodywork on sides – loose the join between the 2 van
Refit doors and bonnet
Interior work
Saturday Night
Spray full van
Sunday Day Till it’s done
Finishing off buffing etc.
Any airbrushing stripes etc.
Fit lights, trim, windows screen etc.
Finish interior
Fit alloys
Any extra work needed on engine fitting drive train etc.
This is just a quick drawing ive done (in paint) to illustrate it better - ive only used red to illustrate what parts are painted - doesnt mean its gonna be in red







mk5 nothing even comes close